Case study – 8 inch mixed black drain pipework

Integrity issue

An 8 inch mixed Black drain pipework was suffering from internal corrosion. Localised internal corrosion had caused severe pitting which was expected to go through wall within months. It was proposed to use a FutureWrap composite repair to reinstate the integrity of the pipework.

Design

The design of the FutureWrap repair was according to ISO 24817.  The design approach was for pipework strengthening and leak sealing. The design parameters were; internal pressure 12.5 bar, temperature 900C, design lifetime 10 years, through wall defect. The repair design resulted in a thickness of 7.6 mm (10 layers) of FutureWrap Glass/LT composite repair with an axial length of 600 mm.

 

Installation

The installation steps are shown in the photographs. The pipework was depressurised. The surface preparation was to ST3. Full QA/QC measurements were made to demonstrate that the FutureWrap repair was applied in accordance with ISO 24817.

 

Summary

A 8 inch mixed black water pipework suffering internal corrosion was repaired using FutureWrap Glass/LT composite repair.  The repair was completed within 2 days allowing the pipework to be re-pressurised returning the pipework to its original integrity.

Engineered Composite Solutions
Abz Business Park, Cirrus Building
6 International Avenue, Dyce Drive
Aberdeen AB21 0BH
t: +44 (0)1224 920 909 | e: sales@ecs-world.co.uk

© Copyright 2020 - all rights reserved. Cookie Policy | Privacy Policy

Engineered Composite Solutions Limited, Company No: ISO 9001 ISO45001 & ISO14001.

CONTACT US